運用作業寬裕達成既定排程期望目標之研究
The design of using float times to fulfill the target of a predetermined schedule
摘要
Many scheduling approaches for generating effective schedules
have been developed in the literature. However, if all the
tasks of the resultant schedule can not be finished at the
production control stage within the planning period, all the
efforts of these are useless. Unfortunately, the management have
to face unexpected disruptions in the shop, when implementing
(1) how to adjust a schedule to be more robust; (2) how to
derive the control priority order for each operation in the
schedule, according to the extent of being deviated from the
schedule; and (3) how to choose the operations for compression
in order to force the orders which will be delayed to be on
schedule again. This thesis presents the concept and the
derivation of the float time for each operation in a schedule.
By using the float times as measures, the approaches to solving
the above problems are developed.
have been developed in the literature. However, if all the
tasks of the resultant schedule can not be finished at the
production control stage within the planning period, all the
efforts of these are useless. Unfortunately, the management have
to face unexpected disruptions in the shop, when implementing
(1) how to adjust a schedule to be more robust; (2) how to
derive the control priority order for each operation in the
schedule, according to the extent of being deviated from the
schedule; and (3) how to choose the operations for compression
in order to force the orders which will be delayed to be on
schedule again. This thesis presents the concept and the
derivation of the float time for each operation in a schedule.
By using the float times as measures, the approaches to solving
the above problems are developed.