平行機台軟體測試排程總權重延遲時間與能源成本最小化
Parallel-machine Scheduling to Minimize Tardiness Penalty and Power Cost in Software Test
摘要
本論文主要在研究考慮軟體測試排程問題中平行機台最小化總權重延遲時間與能量成本,此問題為 NP-hard。在此類問題中,目標任務會有相對應的前置項目需要完成,並且同個前置項目可能同時為不同目標任務的前置,除非在此機台上所有該目標任務的前置項目皆已完成。否則此任務無法在該機台上執行.除此之外,機台可以透過調整處理模式來使任務處理時間減短,更快的模式也需要更高的能量成本。因此每項任務需要決定該在機台上以什麼模式執行。在本篇論文中共提出了兩種整數規劃的模型來解決此問題。另外也提出了數種啟發式演算法.此外我們還提出了蟻群演算法更加一步的求取近似解。最後我們進行實驗及比較,並分析各演算法間的效能。
This paper investigates the problem of minimizing the total weighted tardiness and energy costs with parallel machines in software testing scheduling. The problem is NP-hard. In this kind of problem, each target job has corresponding supporting jobs that need to be completed, and the same supporting job can be the predecessor of multiple target jobs. A job cannot be executed on a machine unless all its supporting jobs on that machine have been completed. Additionally, the processing mode of a machine can be adjusted to shorten the processing time of a job, but a faster mode also requires a higher energy cost. Therefore, each job needs to decide in what mode it should be executed on a machine.
In this paper, we propose two integer programming models to solve the problem. We also propose several heuristic algorithms. In addition, we propose an ant colony algorithm to obtain more approximate solutions. Finally, we conduct experiments and comparisons and analyze the performance of the algorithms.
In this paper, we propose two integer programming models to solve the problem. We also propose several heuristic algorithms. In addition, we propose an ant colony algorithm to obtain more approximate solutions. Finally, we conduct experiments and comparisons and analyze the performance of the algorithms.