利用數值模擬與現地觀測探討水工構造物與保護工法適用性-以大安溪為例

Monitoring Data to Study the Effects of Installing Hydraulic Structures in Rivers and their Protection Works - A Case Study of the Daan River of Taiwan.

檔案

日期

2021

類型

語言

中文

摘要

摘要
近年來臺灣遭受極端氣候影響,強降雨與颱風事件所造成的洪水,對於河川短急的台灣而言,容易造成河川底床沖刷、橋墩周圍沖刷與堤防潰堤的災害發生。大安溪白布帆河段過往遭受許多洪水災害,近年來最為嚴重的一次為2013年蘇力颱風侵蝕白布帆堤防,造成破堤。對於易致災性的河段的水理流況與輸砂現象,以及如何減緩橋墩周遭沖刷情形,實屬重要課題。本研究為掌握大安溪高風險白布帆段之河道穩定及水工構造物之安全評估,以HEC-HMS模擬山區地表逕流,並透過水文模式WASH123D進行該研究區域的校準與驗證。最後藉由二維動床模式CCHE-2D,模擬白布帆大橋於不同重現期流量下,白布帆段及白布帆大橋橋墩河床沖淤趨勢,並探討拋石工法及潛板保護工設立前後,河川流速、底床沖刷深度等變化來推估保護工法的適用性,以提供未來河川治理與橋梁安全管理之參考。
分析結果初步發現,在五年重現期流量,未設置保護工的情況下,P3-site橋墩周遭的流速大小約為5.25 m/s,推估刷深約為1.6 m;而設置拋石後流速大小為4.6 m/s,推估刷深約為1.4 m,設置潛板時,流速為3.49 m/s,推估刷深為1.3 m。拋石工法減緩流速情形約12%;減緩沖刷深度15%。而設置潛板減緩流速約25%;減緩沖刷深度約22%。因此,此區設置潛板之效益優於傳統拋石工法。
In recent years, Taiwan has been affected by extreme weather. Floods caused by short-term heavy rainfalls and typhoon events are likely to cause disasters such as river bed erosion, scouring around bridge piers, and embankment failures in Taiwan, which with features of high slope and short rivers. The Baibufan section in the Daan River region has suffered from many floods in the past. The most serious one in recent years was Typhoon Suli event in 2013, which causing the Baibufan embankment to break. Regarding the water management and sandimet transport in the disaster-prone river section, how to reduce the scour around the bridge piers or embankments, it is an impressing and crucial issue. This study aims to evaluate the river stability and safety conditions of hydraulic structures in the high-risk Baibufan region in Daan River watershed. The HEC-HMS was used to simulate the surface runoff in mountainous areas, and the study area is calibrated and verified through the hydrological model WASH123D. Finally, the two-dimensional movable bed model CCHE-2D was utilized to simulate the scour phenomenon near the Baibufan bridge P3-Site under different flow rates and different recurrence periods. To reduce the impact from scour, two scour countermeasures (e.g., the riprap and submerged vane method) were designed and numerical tested by CCHE-2D. The applicability of the protection methods were estimated by changes in the flow velocity and scour depth for providing guidelines for future river governance and bridge safety management.
The preliminary results of the analysis indicated that in the five-year return period without protection works, the simulated flow velocity and scour depth are about 5.25 m/s and 1.6 m, respectively. With the submerged slab protection method, the simulated flow velocity and scour depth reduce to 3.49 m/s and 1.3 m, respectively. The riprap method can slow down the flow rate by about 12% and reduce the scour depth by 15%. The setting of the submerged vane can slow down the flow rate by about 25%; reduce the depth of the buffer brush by about 22%. Therefore, setting up the submerged vanes in this area is better than the traditional riprap method as to scour.

所屬典藏

土木工程學系
顯示完整詮釋資料 統計資料

引用此條目

陳庭威 (2021). 利用數值模擬與現地觀測探討水工構造物與保護工法適用性-以大安溪為例. https://thesis.lib.nycu.edu.tw/handle/20.500.14371/78079

BibTeX RIS

引用文字依 APA 第 7 版格式自動產生,使用前請再核對。

分享

永久網址:https://thesis.lib.nycu.edu.tw/handle/20.500.14371/78079