建立碰撞檢測機制以輔助建築工程進度之概估
Establishing Collision Detection Mechanism to Assist in Estimating the Progress of Building Construction Project
摘要
若要精準地計算建築工程每月之實際進度,主要乃須依據工地現場人員(例如工地主任或工程師)每天針對各工程項目施工之情況,判斷其完成之數量並紀錄於施工日誌內,累績至每月工作數量後,進而計算實際進度。然而有時工程管理者(工地主任或專案經理)僅需要約略瞭解工程進度是否超前或落後,以利判斷該工程是否需要趕工,故快速地概估工程實際進度有其實務上之需求。為此,本研究根據一系列之前期研究下,嘗試進一步導入建築資訊模型(BIM)與點雲模型新技術,建立一套以碰撞檢測機制為基礎之工程進度概估模式。
本研究所提出概估模式包括五個模組,首先,模組1透過參數化鋼筋建置,於BIM模型中輸入鋼筋參數取代建置鋼筋模型,達到結構平面圖參數化,並撰寫程式以自動計算結構體各工項(鋼筋、模板與混凝土)之數量,整合後輸出所有結構元件資訊與數量。模組2乃以全景相機與空拍機,分別蒐集影像以建置工程內部及外部點雲模型,並結合內外部點雲模型以建置實際進度點雲模型。模組3疊合實際進度點雲模型與BIM模型以執行碰撞檢測,然後根據碰撞檢測結果,辨識結構元件的施工狀態。模組4則建立資料庫儲存各項數據,以提供模組5將元件導入數量與單價,進行計算工程累計完成成本,完成工程進度之概估。
本研究以三件興建中工程進行測試,測試時,案例一及案例二之施工進度分別為基礎工程及結構體完成(但未拆除鷹架階段),其測試結果顯示,案例一因地下室光線不足,導致內部點雲模型建置成效不佳,無法執行模組3套疊BIM模型與點雲模型之碰撞檢測;案例二則因施工鷹架遮擋結構體無法建置模組2之外部點雲模型。整體上,案例一與案例二之測試經驗顯示,使用本模式時須注意結構體應避免遮擋,且在光源不足環境下,須透過人工補光、更換高感光設備或須影像後處理等作法,才能運用本模式進行工程進度之概估。至於案例三之測試過程並無光線不足及結構體遮擋等問題,本研究分別以兩個情境進行測試,經比較本研究模式之進度概估計算結果與該工程廠商提供之進度數據後,其兩者實際進度之差異小,顯示本研究模式具有可行性。後續研究主要建議應進一步電腦化本研究模式,以利提升其在實務上之運用效益。
本研究所提出概估模式包括五個模組,首先,模組1透過參數化鋼筋建置,於BIM模型中輸入鋼筋參數取代建置鋼筋模型,達到結構平面圖參數化,並撰寫程式以自動計算結構體各工項(鋼筋、模板與混凝土)之數量,整合後輸出所有結構元件資訊與數量。模組2乃以全景相機與空拍機,分別蒐集影像以建置工程內部及外部點雲模型,並結合內外部點雲模型以建置實際進度點雲模型。模組3疊合實際進度點雲模型與BIM模型以執行碰撞檢測,然後根據碰撞檢測結果,辨識結構元件的施工狀態。模組4則建立資料庫儲存各項數據,以提供模組5將元件導入數量與單價,進行計算工程累計完成成本,完成工程進度之概估。
本研究以三件興建中工程進行測試,測試時,案例一及案例二之施工進度分別為基礎工程及結構體完成(但未拆除鷹架階段),其測試結果顯示,案例一因地下室光線不足,導致內部點雲模型建置成效不佳,無法執行模組3套疊BIM模型與點雲模型之碰撞檢測;案例二則因施工鷹架遮擋結構體無法建置模組2之外部點雲模型。整體上,案例一與案例二之測試經驗顯示,使用本模式時須注意結構體應避免遮擋,且在光源不足環境下,須透過人工補光、更換高感光設備或須影像後處理等作法,才能運用本模式進行工程進度之概估。至於案例三之測試過程並無光線不足及結構體遮擋等問題,本研究分別以兩個情境進行測試,經比較本研究模式之進度概估計算結果與該工程廠商提供之進度數據後,其兩者實際進度之差異小,顯示本研究模式具有可行性。後續研究主要建議應進一步電腦化本研究模式,以利提升其在實務上之運用效益。
Precise determination of monthly construction progress mainly relies on on-site superintendents or engineers to document the number of work items completed every day on the construction log. Such daily documentation facilitates the end-of-month progress assessment. However, in practice, a quick and rough assessment of construction progress sometimes is critical for construction managers (superintendents or project managers) to determine whether the project is ahead or behind in the schedule, thereby assessing the need for schedule acceleration. For this reason, based on several previous studies, this research establishes a collision-detection-mechanism-based model for estimating construction progress by combining Building Information Model (BIM) and point cloud model techniques.
The proposed model comprises five modules. Module 1 develops parameterized rebar configuration, in which rebar parameters are input into a BIM (as opposed to establishing a rebar model) to parameterize a structure’s floor plan. A self-developed program then automatically takes off the quantities of structural components (rebar, formwork, and concrete) required for each work item and exports the take-off results. Module 2 involves the use of panoramic cameras and drone cameras to collect images for establishing the internal and external point cloud models of the building facilities for a construction project. The two models are then combined to create an as-built point cloud model for illustrating the actual construction progress. In Module 3, this as-built point cloud model and BIM are superimposed to enable collision detection, the results of which are used to determine the construction status of each structural component. Module 4 establishes a database to store various information, which is then input into Module 5. By considering the quantities and unit prices of completed components, Module 5 estimates the cumulative completed costs (that is, budgeted costs of work performed) of the project to estimate the current construction progress.
The proposed model was tested using three ongoing construction projects (Projects 1–3). At the time of the tests, Projects 1 and 2 had completed the construction of the foundation and structure (but the scaffolding had not been removed), respectively. The test results revealed that the lack of lighting in the basement in Project 1 undermined the accuracy of the internal point cloud model, which precluded the superimposition of the BIM and point cloud model for collision detection in Module 3. The view of the structure in Project 2 was obstructed by the scaffolding, which hindered the establishment of the external point cloud model in Module 2. Overall speaking, the test results of Projects 1 and 2 demonstrated that the proposed model should mainly be applied to structures with unobstructed views. Methods such as artificial lighting, installation of high-sensitivity cameras, or image postprocessing should be used when the lighting of the structure is insufficient. With sufficient lighting and an unobstructed view, the structured in Project 3 was tested in two scenarios. These estimation results obtained from the proposed model were verified to differ slightly from the actual construction progress data (provided by the case construction company), thereby confirming the feasibility of the proposed model. Future researchers may computerize the proposed model to further enhance its practicality.
The proposed model comprises five modules. Module 1 develops parameterized rebar configuration, in which rebar parameters are input into a BIM (as opposed to establishing a rebar model) to parameterize a structure’s floor plan. A self-developed program then automatically takes off the quantities of structural components (rebar, formwork, and concrete) required for each work item and exports the take-off results. Module 2 involves the use of panoramic cameras and drone cameras to collect images for establishing the internal and external point cloud models of the building facilities for a construction project. The two models are then combined to create an as-built point cloud model for illustrating the actual construction progress. In Module 3, this as-built point cloud model and BIM are superimposed to enable collision detection, the results of which are used to determine the construction status of each structural component. Module 4 establishes a database to store various information, which is then input into Module 5. By considering the quantities and unit prices of completed components, Module 5 estimates the cumulative completed costs (that is, budgeted costs of work performed) of the project to estimate the current construction progress.
The proposed model was tested using three ongoing construction projects (Projects 1–3). At the time of the tests, Projects 1 and 2 had completed the construction of the foundation and structure (but the scaffolding had not been removed), respectively. The test results revealed that the lack of lighting in the basement in Project 1 undermined the accuracy of the internal point cloud model, which precluded the superimposition of the BIM and point cloud model for collision detection in Module 3. The view of the structure in Project 2 was obstructed by the scaffolding, which hindered the establishment of the external point cloud model in Module 2. Overall speaking, the test results of Projects 1 and 2 demonstrated that the proposed model should mainly be applied to structures with unobstructed views. Methods such as artificial lighting, installation of high-sensitivity cameras, or image postprocessing should be used when the lighting of the structure is insufficient. With sufficient lighting and an unobstructed view, the structured in Project 3 was tested in two scenarios. These estimation results obtained from the proposed model were verified to differ slightly from the actual construction progress data (provided by the case construction company), thereby confirming the feasibility of the proposed model. Future researchers may computerize the proposed model to further enhance its practicality.