以關鍵鏈專案管理為基礎探討產品專案無法如期之因素 -以台灣B公司為例

Explore Factors that Product Projects cannot Complete on Schedule Based on Critical Chain Project Management - A Case Study of B Company in Taiwan

檔案

日期

2023

類型

語言

中文

摘要

高德拉特(Goldratt)博士利用限制理論(Theory of Constraints, TOC)尋找專案管理方法的突破,在1997年發明關鍵鏈(Critical Chain),在全世界已許多企業廣泛或嘗試應用關鍵鏈專案管理(Critical Chain Project Management, CCPM)的案例,如英特爾(Intel)、德州儀器(TI)、福特汽車(Ford)、漢威聯合國際(Honeywell International)等,在導入關鍵鏈專案管理之後,皆獲得顯著的改善成效,大幅縮短專案時程。本研究欲探討利用關鍵鏈專案管理的觀念來檢視於IC設計公司執行新產品專案活動,進一步了解目前個案公司的專案行為與關鍵鏈專案管理觀念實際差異以及需要改善執行痛點。從個案可以發現不良多工、過多的個人緩衝時間保留、帕金森定律與學生症候群是可能造成專案時程不能準時的各種因素。但個案公司內部員工卻不完全認同,他們認為人力缺乏、工作任務過重、多數任務重疊……等等才是專案時程不準時的主因,因此想透過本研究來詳細探討,並在獲得結論之後給予個案公司相關專案管理的建議與改善方向。
Dr. Goldratt used Theory of Constraints (TOC) to find a breakthrough in project management methods and invented the Critical Chain in 1997. Many companies around the world have widely or tried to apply Critical Chain Project Management cases, such as Intel, Texas Instruments, Ford Motor, Honeywell International, etc., have achieved remarkable results after the introduction of critical chain project management The improvement effect, greatly shorten the project time schedule. This study intends to explore the use of the concept of critical chain project management to examine the implementation of new product project activities in IC design companies, to further understand the actual differences between the current project behavior of the case company and the concept of critical chain project management, as well as the pain points that need to be improved. From individual cases, it can be found that bad multitasking, excessive personal buffer time retention, Parkinson's law and student syndrome are various factors that may cause project schedules to be unpunctual.
顯示完整詮釋資料 統計資料

引用此條目

林志豪 (2023). 以關鍵鏈專案管理為基礎探討產品專案無法如期之因素 -以台灣B公司為例. https://thesis.lib.nycu.edu.tw/handle/20.500.14371/83072

BibTeX RIS

引用文字依 APA 第 7 版格式自動產生,使用前請再核對。

分享

永久網址:https://thesis.lib.nycu.edu.tw/handle/20.500.14371/83072